Monday 2 May 2016

Accounting Standard – 7
Construction Contract

1.       Applicability and Nature : This AS is applicable from 01-04-2002 onwards and Mandatory for construction companies only.
2.       Objective:-The main objective of this AS is to prescribe rule for recognition of revenue and cost for a construction contract because a construction contract may take more than one accounting year to be completed.
3.       Meaning of Construction Contract:-As per the provision of AS-7 Construction Contract is a contractual agreement where contractor constructs Asset as per the requirement of customer. These construction contracts may be for construction of Building, roads and etc.
4.       Types of construction contracts:
(i)                  Fixed Price Contract:- A fixed price contract is that in which a fixed price is agreed to be paid to the contractor.
(ii)                Cost plus Contract:- The contract of construction for which contractor is paid following to payments:
(a)    Cost Incurred for construction,
(b)   A Fixed % of profit on Cost.
Note- There will be no loss under this type of contract to the contractor under this type of contracts.
5.       Meaning of cost escalation:- Cost Escalation is an agreement between contractor and contractee whereby contractee agreed to pay an extra amount on % basis to contractor for an increase in the cost of material and labour beyond a specified limit.
6.       Accounting for Fixed Price Contract:-
Revenue is recognized as per the provision of
Para-22, Para-23, Para-31

Para-22
Following steps are used for revenue recognition
Step-1   Calculate Completion Stage as follows:

                = Actual Cost/total estimated cost X100

Step-2   Contract Revenue

                = Contact Price X % of Completion

Example-1
Actual Cost till Date                                                                                        Rs.2,00,000
Total Estimated Cost                                                                                      Rs.5,00,000
Contract Price                                                                                                   Rs.6,00,000

                Sol.
                Step-1                   % of Completion= 20/50 X 100 = 40%

                Step-2                   Contract Revenue = Contract Price X % of completion
                                                                                = 60,00,000 X 40 % = 24,00,000

                Example-2
                                                                                                                                                                                (Rs. in Lacs)

Year 1
Year 2
Year 3
Contract Price
60
60
60
Actual Cost
10
25
45
Total Estimated Cost
50
50


Contract Revenue and Profit for first year:
                                Completion Stage = 10/50 X 100 = 20%
               
                                Contract Revenue = 60 X 20% = 12 Lacs

                                Contract Profit = Revenue – Cost = 12-10 = 2 Lacs

Contract Revenue and Profit for Second year:
Completion Stage = 25/50 X 100 = 50%
               
                                Contract Revenue = 60 X (50%- 20%) = 18 Lacs

                                Contract Profit = Revenue – Cost = 18-(25-10) = 3 Lacs

Contract Revenue and Profit for Second year:
               
                                Contract Revenue = 60 – 18 - 12 = 30 Lacs

                                Contract Profit = Revenue – Cost = 30-(45-25) = 10 Lacs

Para-23
In case there is a difference in % of completion as per completion method and physical construction of asset then contract Revenue should be computed by survey method.
Under this specified method contract revenue should be recognized on the basis of certificate issued by surveyor.

Para-23
As per the provision of AS-7, application of para-31 can be made only if total estimate is not available. In this specified case, contract revenue will be equal to actual cost incurred by contractor an there will be no profit or loss.

7.       Variation in Contract Work:-A variation is an instruction by customer for a change in the scope of work to be performed under the contract revenue.
Additional Assets:- The Construction of additional Asset should be treated as a separate contract if:
(i)                  The asset differs significantly in design, technology
(ii)                If price of the asset is negotiated without regard to the original contract price.
8.       Claim :-The amount received by contractor in addition to the contract price is called as claim. This may be collected from contractee because of the following reason:
(i)                  Customer caused delay,
(ii)                Error in specification of designs
(iii)               Disputed variation in the contract work.
9.       Inventive:- The extra payment made by contractee to the contractor for achieving specified standards like- completion of construction before the time specified.
10.   Contract revenue includes the following:
(i)                  Initial contract price
(ii)                Variations in contract
(iii)               Claims
(iv)              Inventive payments.
Note- A variation is included in the contract revenue when it is probable that the customer will approve the variation and the amount of revenue can be measured reliably.
11.   Combining of contracts:
For the purpose of accounting, contracts are combined (i) if the negotiation of the contracts is made in a single package, (ii) the contracts are so closely interrelated that they are, in effect , part of single project with an overall profit margin and (iii) the contracts are performed concurrently or continuous sequence.
12.   Segmenting of contract.
For the purpose of accounting segmenting of contract is done if (i) Each Contract is supported by separate proposals, (ii) separate negotiation is made for each assets  and the contractor and the contractee are in position to accept or reject any contract. (iii) the cost and revenue of each assets can be identified.
13.   Contract Cost include the following:
(i)                  Direct Cost:- Site Labour Cost, Site supervision, cost of material, depreciation of FA, hire charge of FA, claims of third party etc.
(ii)                Allocable Cost: The cost which is attributable to contract activity in general and can be allocated to the contract. It includes the following:
Insurance, construction Overhead, Borrowing Costs etc.

(iii)               Special Cost:- The cost which is incurred on the basis of specification given by customer.

No comments:

Post a Comment